Construction state of the U ONE residential complex as of 15.08.2023
Section 3
Laying of the outer walls of the 13th floor has begun.
Glazing of the 9th floor is completed.
Completed laying of the internal walls of the 7th floor.
Plastering of the staircases is in progress.
Roofing has begun.
Section 4
Installation of the floor slab of the 12th floor is in progress.
Laying of the external walls of the 7th floor is in progress.
Section 2
Installation of vertical elements of the 8th floor continues.
Section 1
Installation of monolithic grillage is 95% complete.
Installation of vertical elements of the 1st floor is 80% complete.
Work is underway on the installation of external water supply and sewerage networks.