Construction state of the Union residential complex as of 27.04.2023
Section A
Transferred to the management company.
Section B
Finishing of the entrance is 90% complete.
The lobby is 50% finished.
Section C
Installation of water supply and sewerage networks is in progress.
The installation of internal power supply is in progress.
Facade finishing works are 75% complete.
Plastering of apartments and staircases has been completed.
Works on finishing the entrance have begun.
Section D
Concreting of vertical elements of the 3rd floor is underway.
Installation of the floor slab of the 2nd floor is in progress.
Concreting of vertical elements of the 3rd floor has begun.
Section E
Concreting of vertical elements of the basement of the 2nd floor is completed.
Concreting of vertical elements of the 1st floor has begun.
Formwork for the floor slab of the 2nd floor has begun.
Commercial
Laying of the outer walls of the commercial building continues.
Find out first about the company's news