Construction state of the Union residential complex as of 29.06.2023
Section A
Finishing of the entrance is completed.
Section B
Finishing of the entrance is completed.
Finishing of the hall is 90% complete.
Section C
Installation of internal water supply and sewerage networks is completed.
Installation of in-house electricity supply is completed.
The facade is 90% finished.
Finishing of the entrance is 85% complete.
Section D
Concreting of vertical elements of the 6th floor is completed.
Reinforcement of the floor slab of the 6th floor is in progress.
Section E
Concreting of vertical elements of the 7th floor is in progress.
Commercial section
Completion of the exterior walls of the commercial building.