Construction state of the Union residential complex as of March 01.03.2023
Section A
Finishing of the entrance is completed.
The lobby is 70% finished.
The paving stones for the entrance to the section have been laid.
Section B
Finishing of the entrance is 90% complete.
Section C
Installation of water supply and sewerage networks is in progress.
The installation of in-building electricity supply has begun.
Facade finishing works have been completed by 40%.
Section D
Concreting of the vertical elements of the basement has been completed.
Concreting of the basement floor slab is completed.
Section E
Pile driving works have been completed.
Work is underway to install grillage.
Concreting of vertical elements of the basement has begun.
Commerce
Concreting of the floor slab is completed.
Laying of the outer walls of the commercial building has begun.