Construction stateof the Parkova Alley residential complex as of 29.08.2023
Section 3
Interior finishing works are 90% complete.
Installation of the elevator is completed.
Section 3a
The interior decoration is 60% complete.
Installation of the elevator has begun.
Section 3b
The installation of vertical elements of the 9th floor continues.
Laying of the internal walls of the 3rd floor is completed.
Laying of the external walls of the 4th floor is completed.
Glazing of the 2nd floor is completed.
Section 3c
Installation of vertical elements of the 11th floor continues.
Completion of the exterior walls of the 5th floor.
Completed laying of the internal walls of the 3rd floor.
Glazing of the 1st floor has begun.
Section 3g
The digging of the pit is completed.
Section 3d
Installation of the basement floor slab is in progress.
Section 3e
Installation of the foundation slab is completed.
Find out first about the company's news