Construction status of the Parkova Alley residential complex as of 24.07.2023
Section 3
Facade works have been completed.
The interior decoration is 80% complete.
Section 3a
The facade has been completed.
The interior decoration works are completed by 30%.
Section 3b
Installation of vertical elements of the 6th floor is completed.
Installation of the floor slab of the 7th floor is in progress.
Laying of external and internal walls of the 2nd floor is completed.
Laying of the external walls of the 3rd floor is in progress.
Section 3c
Installation of the floor slab of the 9th floor is in progress.
Completed laying of external and internal walls of the 2nd floor.
Laying of the outer walls of the 3rd floor is completed.
Laying of the outer walls of the 4th floor is in progress.
Section 3g
Preparatory work is underway.
Section 3d
Installation of vertical elements of the basement continues.
Section 3e
Reinforcement of the foundation slab is in progress.