Construction state of the residential complex “Avtorskyi” as of 09.05.2023
Sections 1-2
Finishing works on the stairwells in section 2 have been completed.
Installation of elevators in sections 1-2 has been completed.
Installation of slope-forming screeds has been completed.
Sections 3-4
Plastering of the interior walls of penthouses in section 3 is completed.
Works on waterproofing of the parking lot floor slab in sections 3-4 are in progress.
Works on the arrangement of internal communications of the parking lot in sections 3-4 are in progress.
Improvement
Installation of the lifting platform for garbage cans has been completed.