Sections 1-2
Works are underway to improve the adjacent territory.
The industrial floor of the parking lot is 80% complete.
The waterproofing of the parking lot floor slab is 80% complete.
Installation of staircase railings in section 2 is completed.
Works on parking lot lighting are in progress.
Sections 3-4
Finishing of corridors in section 3 is completed.
Works on waterproofing of the parking lot floor slab are in progress.
Works on the arrangement of internal communications of the parking lot in sections 3-4 are in progress.
Installation of elevators in sections 3-4 is completed.
The installation of terrace boards on the terraces of penthouses in sections 3-4 has been completed.
Works on finishing balconies with ceramic tiles in section 3 are completed.
Works on finishing balconies with ceramic tiles in section 4 have begun.
Works on the improvement of the adjacent territory of the residential complex are ongoing.