Construction state of the residential complex “MAIN HOUSE” as of 10.02.2023
Section No. 1
Facade works are 80% complete.
Entrances are 30% finished.
Installation of entrance doors to apartments has begun.
Section No. 2
Facade works are completed by 40%.
The roof is 20% complete.
Installation of waterproofing of the 2nd bay of the parking lot has begun.
Parking lot
Paving is 30% complete.
Installation of the floor slab of the 3rd bay of the parking lot is completed.