Construction state of the residential complex “MAIN HOUSE” as of 01.16.2023
Section No. 1
Facade works are nearing completion.
Finishing of entrances is 30% complete.
Section No. 2
Facade works are 40% complete.
The roof is 20% complete.
Parking lot
Paving is 30% complete.
Installation of the parking lot foundation slab is completed.
The construction of vertical elements of the parking lot has begun.