Dynamics of construction of the Parkova Alley residential area: February – April 2023
We are increasing the pace of construction of new sections of a large-scale residential complex in a cozy suburb of Ivano-Frankivsk. The warm spring weather and the desire to fulfill our customers' dream of a new cozy home help us to do this.
Check out the growth dynamics of Parkova Alley since February this year:
Section 3
The masonry of the external and internal walls is completed, and the roof is installed.
The installation of internal electrical networks, water supply and sewage networks has been completed.
The installation of industrial flooring has been completed.
Plastering of apartments is in progress.
Facade works and glazing are in progress.
Section 3a
External and internal walls have been completed,
The roof has been completed.
Glazing and facade works are in progress.
Installation of internal electrical, water supply and sewage networks is in progress.
Section 3b
The 1st-3rd floors have been erected.
Installation of vertical elements of the 4th floor is in progress.
Section 3c
The 1st-3rd floors have been erected.
Landscaping
The paving of sections 4, 5, 6, 7 has been completed.
And the best news is that sections 4, 5, 6 and 7 have been handed over to the management company.