Dynamics of construction of the Parkova Alley residential area: February – September 2023 💚
We continue to build our projects without resting on our laurels. Every month we are getting closer to the completion of construction. We want our buyers to enjoy living in the new sections of the housing estate.
Evaluate the growth dynamics of the residential complex over the past six months:
💨 Section 3
The roof has been installed.
Installation of internal electrical networks has been completed.
Works on the installation of internal water supply and sewage networks have been completed.
Installation of industrial flooring has been completed.
Facade works have been completed.
Installation of the lift has been completed.
The interior decoration of the entrance is 90% complete.
Installation of doors has begun.
Connection of gas communications to apartments has begun.
The installation of concrete screed of the basement storerooms has begun.
Section 3a
All internal and external walls have been laid.
The roof has been installed.
Work has been completed on the installation of internal electrical networks.
Works on the installation of internal water supply and sewage networks have been completed.
The facade has been completed.
Interior finishing works have been completed by 80%.
Installation of the lift is in progress.
Installation of doors has begun.
💨 Section 3b
The 1st-9th floors have been completed
Concreting of vertical elements of the 10th floor has begun.
Laying of the external walls of the 2nd-6th floors has been completed.
Laying of the internal walls of the 2nd and 3rd floors has been completed.
Laying of the internal walls of the 4th floor has begun.
Glazing of the 1-3rd floors has been completed.
Glazing of the 4th floor has begun.
Section 3c
The 1st-11th floors have been erected.
Laying of external walls of the 2nd-6th floors has been completed.
Laying of the internal walls of the 2-3rd floors has been completed.
Laying of the internal walls of the 4th floor has begun.
Glazing of the 1-3rd floors has been completed.
Section 3g
Digging of the pit is completed.
Concreting of the foundation slab has been completed.
💨 Section 3d
The foundation slab has been installed.
Installation of the basement floor slab.
Concreting of vertical elements of the 1st floor has been completed.
Concreting of the floor slab of the 1st floor has been completed.
Concreting of vertical elements of the 2nd floor has begun.
Section 3e
Excavation of the pit is completed.
The foundation slab has been installed
Installation of vertical elements of the basement has begun.
💨 Sections 4-7
Interior decoration of the entrances has been completed.
Plastering of apartments has been completed.
Transferred to the service company.
🌳 Landscaping
Paving stones have been laid near sections 4-7.
Landscaping of the territory has been completed.