Dynamics of construction of the Parkova Alley residential area: July 2022 – February 23
One of the largest residential complexes by blago continues to grow. The large-scale project of multi-comfortable housing is growing thanks to new sections, which we are successfully implementing on schedule and according to plan. From July 2022:
Section 3
The 5th-11th floors have been completed. The internal walls of the 2nd-10th floors and the external walls of the 2nd-11th floors have been built. Glazing is in progress.
Section 3a
The 6th-11th floors have been erected. The internal walls of the 2-10th floors and the external walls of the 2-11th floors have been erected. Glazing is in progress.
Section 3b
The basement and 1st residential floors have been completed. The construction of the 2nd floor is in progress.
Section 3c
Construction has begun. The basement and 1st residential floors have been completed. The construction of the 2nd floor is underway.
Section 4
Facade glazing and facade works are completed. Plastering of garages is completed. Installation of internal networks has been completed. The interior decoration of the entrances is nearing completion.
Section 5
Works on internal networks (water supply and sewerage) are completed.
Interior finishing of entrances and plastering of apartments is nearing completion.
Sections 6-7
Installation of elevators has been completed. Finishing of the halls is completed. The adjacent territory has been landscaped. Both sections have been handed over to the management company.
Thanks to modern technologies, high-quality materials and experienced specialists, we continue to create comfortable energy-efficient housing in the city.