We are proud to see the new sections being built and enthusiastically look at the sections that are nearing completion. And today we are sharing the results of the construction of the Union residential complex since April this year:
Section A
Finishing of the entrance and hall is completed.
Handed over to the management company.
Section B
Finishing of the entrance is completed.
The hall is 90% finished.
Handed over to the management company.
Section C
Plastering of apartments and staircase is completed.
Installation of internal water supply and sewerage networks is completed.
Installation of in-building power supply networks is completed.
Finishing works on the entrance are completed.
Finishing works on the facade are completed.
The lobby is being finished.
Handed over to the management company.
Section D
Residential floors 2-8 are completed.
The construction of the 9th residential floor is underway.
The outer walls of the 2nd-5th residential floors have been built.
The internal walls of the 2nd residential floor have been constructed.
Glazing of the 1st residential floor is in progress.
Section E
Residential floors 1-9 have been erected.
Concreting of vertical elements of the 10th residential floor is in progress.
The outer walls of the 1st-5th residential floors have been erected.
The internal walls of the 1st residential floor are being built.
Glazing of the 1st residential floor is in progress.
Commercial
The outer walls of the commercial building have been erected.
Commercial glazing is in progress.