0
We will call you back in 25 seconds
Order a call

Dynamics of construction of the residential complex “Union”: April – September 2023

Dynamics of construction of the residential complex “Union”: April – September 2023
Dynamics of construction of the residential complex “Union”: April – September 2023
Dynamics of construction of the residential complex “Union”: April – September 2023
Dynamics of construction of the residential complex “Union”: April – September 2023
Dynamics of construction of the residential complex “Union”: April – September 2023

01 /01

Every month we assess the growth of new sections and record changes at the construction site. Find out about the implementation of the Union RC over the past six months in the updated report.   🔸 Section A Finishing of the entrance is completed. Finishing of the hall is completed. Transferred to the management company.   Section B Finishing of the entrance is completed. The hall is 90% finished. Transferred to the management company.   🔸 Section B Plastering of apartments and staircase is completed. Installation of in-house water supply and sewerage networks has been completed. Installation of in-building power supply networks is completed. Finishing works on the facade are completed. Finishing works on the entrance are completed. The lobby is 90% finished. Transferred to the management company.   🔸 Section D Completed monolithic works on the section. The outer walls of the 1-7th floors have been built. The laying of the outer walls of the 8th floor continues. The internal walls of the 1-3rd floors have been built. Laying of the internal walls of the 4th floor is in progress. The parapet is being laid.   🔸 Section D The 2nd-9th floors have been erected. Concreting of vertical elements of the 10th floor is underway. The outer walls of the 1st-7th floors have been erected. Laying of the external walls of the 8th floor is in progress. The internal walls of the 1st floor have been constructed. Laying of the internal walls of the 2nd floor is underway. The laying of the parapet is underway.   🔸 Commerce Completed laying of external walls. Glazing is completed.
envelope

Find out first about the company's news