IQ House construction dynamics: July 2022 – February 2023

IQ House construction dynamics: July 2022 – February 2023
As a technology company, blago continues processes at all construction sites and implements many other projects to make you enjoy life in the city. And today we will show you the dynamics of the IQ House construction from July 2022. Section 1 The 1st floor has been completed. The construction of the 2nd floor has begun. Section 2 The 1st-5th floors have been completed. The outer walls of the 2nd floor have been built. Masonry of the internal walls of the 2nd floor is 80% complete. Section 3 The 1st-3rd floors have been erected. The construction of the 4th floor has begun. Without slowing down, we continue to create a modern environment for a comfortable life. Live smart with IQ House.