Construction state of the residential complex A5 as of January 23, 2023
Completion of the exterior walls of the 1st floor.
Laying of the internal walls of the 1st floor is in progress.
Laying of the outer walls of the 2nd floor is in progress.
Preparatory work for the floor slab of the 7th floor has begun.
Laying of the internal walls of the 3rd floor is 25% complete
Laying of the external walls of the 3rd floor has been completed by 5%.