Construction state of the Family Plaza residential complex as of 12.10.2022
Section 1
- Finishing of the entrance is completed.
- The lobby is being finished.
Section 2
- Installation of the elevator is completed.
- Finishing of the entrance is in progress.
- Finishing of the hall has begun.
Section 3
- Installation of the elevator is completed.
- Completed work on internal house networks (water supply and sewerage).
- Works on internal house networks (electricity supply) are in progress.
- Plastering of apartments has begun.
Section 4
- Finishing of the facade is completed.
- Installation of the elevator is completed.
- Works on internal house networks (water supply and sewerage) are in progress.
- Work is underway on the internal house networks (electricity).
- Plastering of apartments has begun.
Section 5
- Completed laying of external and internal walls of the basement.
Section 6
- Monolithic works are completed.
- Laying of the outer walls of the 8th floor is completed.
- Laying of the internal walls of the 4th and 5th floors is in progress.
Section 7
- Concreting of vertical elements of the 4th floor is completed.
- Formwork for the floor slab of the 4th floor is in progress.
- Work has begun on the laying of the outer walls of the 1st floor.
Section 8
- Concreting of the vertical elements of the basement has been completed.
- The formwork of the basement floor slab is in progress.
Section 12
- Completed laying of the outer walls of the 10th floor.
- Work is underway on the internal house networks (water supply and sewerage).
- Glazing works are in progress.
- Facade finishing has begun.
- Plastering of apartments has begun.