Construction state of the Family Plaza residential complex as of January 19, 2023
Section 1
Finishing of the hall is completed.
Section 2
Finishing of the entrance is nearing completion.
Finishing of the hall is nearing completion.
Section 3
Finishing of the entrance is 50% complete.
Section 4
Finishing of the entrance is 50% complete.
Section 5
Completed glazing of the section.
The facade is 50% complete.
Work is underway on in-house networks (electricity).
Plastering of apartments has begun.
Section 6
The masonry of the internal walls of the 10th floor has been completed.
The masonry of the garages in the basement is completed.
Works on internal house networks (water supply and sewerage) are in progress.
Section 7
Laying of the outer walls of the 6th floor has begun.
The laying of the internal walls of the 5th floor has been completed.
Section 8
Concreting of the floor slab of the 1st floor is completed.
Laying of the outer walls of the 1st floor has begun.
Section 12
Finishing of the facade is completed.
Plastering of apartments is completed.
Works on in-house networks (electricity supply) are in progress.
Parking lot
Concreting of the foundation slab of the second bay parking lot has been completed.
Concreting of the vertical elements of the parking lot slab of the second bay is in progress.
Reinforcement of the floor slab of the second section has begun.
Find out first about the company's news