Construction state of the residential complex “IQ House” as of February 15, 2023
Section 1
Installation and concreting of the 1st floor has been completed.
The construction of vertical elements of the 2nd floor has begun.
Section 2
Installation of the floor slab of the 4th floor is completed.
Installation of the floor slab of the 5th floor is completed.
The construction of vertical elements of the 5th floor is completed.
Completion of the exterior walls of the 2nd floor.
Laying of the internal walls of the 2nd floor is 80% complete.
Section 3
The construction of vertical elements of the 3rd floor is completed.
The construction of the monolithic slab of the 3rd floor is completed.
Installation of the floor slab of the 3rd floor is completed.
Installation and concreting of the 4th floor is completed.