Construction state of the residential complex Parkova Alley as of 10.31.2022
Section 3
Installation of the floor slab on the 10th floor is in progress.
Laying of external and internal walls of the 5th, 6th, 7th floors is in progress.
Section 3a
Installation of the floor slab of the 10th floor is in progress.
Laying of the internal and external walls of the 6th, 7th, 8th floors is in progress.
Section 3b
Installation of the basement floor slab is completed.
Section 3c
Installation of vertical elements of the basement floor is completed.
Section 4
Facade works on the 1st floor are in progress.
The interior decoration of the entrances is 40% complete.
Plastering of apartments on the 7th floor is in progress.
Section 5
The interior decoration of the entrances is 40% complete.
Facade works on the 1st floor are in progress.
Sections 6-7
The lobby is being finished.