Construction state of the residential complex “U ONE” as of 01.12.2022
Section 3
Work is nearing completion on pressing reinforced concrete piles.
The installation of monolithic grillage is 60% complete.
Installation of vertical elements of the 1st floor is in progress.
Section 4
Reinforced concrete piles have been pressed by 30%.
Installation of monolithic grillage is in progress.
Section 2
Preparatory work has begun.