Construction state of the residential complex “U ONE” as of 02.01.2023
Section 3
Works on pressing reinforced concrete piles have been completed.
Works on the installation of monolithic grillage have been completed.
Installation of vertical elements of the 1st floor is completed.
Installation of the 1st floor slab is completed.
Section 4
Reinforced concrete piles have been pressed by 70%.
Works on the installation of monolithic grillage by 30%.
Section 2
Work has begun on the pressing of reinforced concrete piles.