Construction status of the U ONE residential complex as of 02.02.2023

Construction status of the U ONE residential complex as of 02.02.2023
Construction status of the U ONE residential complex as of 02.02.2023
Construction status of the U ONE residential complex as of 02.02.2023
Construction status of the U ONE residential complex as of 02.02.2023

01 /01

Section 3 Installation of vertical elements of the 2nd and 3rd floors is completed. The formwork of the floor slabs of the 2nd and 3rd floors has been completed. Section 4 Reinforced concrete piles have been pressed by 90%. The installation of monolithic grillage is 50% complete. Section 2 Reinforced concrete piles have been pressed by 70%.