Construction status of the U ONE residential complex as of 02.02.2023
Section 3
Installation of vertical elements of the 2nd and 3rd floors is completed.
The formwork of the floor slabs of the 2nd and 3rd floors has been completed.
Section 4
Reinforced concrete piles have been pressed by 90%.
The installation of monolithic grillage is 50% complete.
Section 2
Reinforced concrete piles have been pressed by 70%.