Construction state of the Union residential complex as of 12.28.2022
Section A
Finishing of the entrance is nearing completion.
The paving for the entrance to the section is completed.
Section B
Finishing of the entrance is nearing completion.
Finishing works on the facade are nearing completion.
Section C
Laying of inter-apartment and interior walls is completed.
Glazing of the 7th floor is completed.
Section D
Grillage is being completed.
Section E
Works on pile driving are nearing completion.
Commerce
Concreting of the floor slab is completed.
The parapet has been completed.