Construction state of the Union residential complex as of 11.30.2022
Section 1
The entrance is 80% finished.
Finishing works on the commercial floor facade have been completed.
Section 2
The entrance is 50% finished.
The facade is 70% complete.
Installation of the elevator shaft has been completed.
Installation of the elevator is completed.
Section 3
Laying of masonry and inter-apartment walls of the 7th floor is in progress.
Glazing of the 6th floor is in progress.
Section 4
Completed work on pile driving.
The installation of grillage has begun.
Section 5
Work has begun on pile driving.
Commerce
Concreting of the floor slab is completed.