Construction state of the Parkova Alley residential complex as of 12.26.2022
Section 3
Installation of the floor slab of the 11th floor is in progress.
Laying of the external walls of the 9th floor is in progress.
Laying of the internal walls of the 8th and 9th floors is in progress.
Installation of glazing has begun.
Section 3a
Laying of the outer walls of the 10th floor continues.
Laying of the internal walls of the 9th and 10th floors is in progress.
Monolithic works are completed.
Section 3b
Installation of vertical elements of the 1st floor has begun.
Section 3c
The formwork of the basement floor slab has been completed.
Section 4
The interior decoration of the entrances is nearing completion.
Plastering of apartments on the 10th floor is in progress.
Section 5
Interior finishing of the entrances is nearing completion.
Plastering of apartments on the 8th floor is in progress.
Sections 6-7
Finishing of the lobby is completed.