0
We will call you back in 25 seconds
Order a call

Construction state of the residential complex “Parkova Alley” as of 11.30.2022

Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022
Construction state of the residential complex “Parkova Alley” as of 11.30.2022

01 /01

Section 3 Installation of the floor slab on the 11th floor is in progress. Laying of external walls of the 8th floor and internal walls of the 7th and 8th floors is in progress. Section 3a Installation of the floor slab of the 11th floor is completed. The laying of the outer walls of the 8th and inner walls of the 7th and 8th floors is in progress. Section 3b Installation of the basement floor slab is completed. Section 3c Preparatory work for the installation of formwork for the basement floor slab has begun. Section 4 Completed facade works on the 1st floor. The interior decoration of the entrances is 60% complete. Plastering of apartments on the 10th floor is in progress. Section 5 The interior decoration of the entrances is 60% complete. Facade works on the 1st floor are completed. Plastering of apartments on the 7th floor is in progress. Sections 6-7 The lobby is 70% finished.
envelope

Find out first about the company's news