Construction state of the Manhattan residential area as of 01.28.2023
House 5
The entrance is 70% finished.
Installation of balcony railings is in progress.
House 6
Installation of heating risers has been completed.
Installation of aluminum glazing is completed.
Installation of metal-plastic glazing is nearing completion.
The facade is 30% finished.
Plastering of apartments has begun.
House 7
Installation of the floor slab of the commercial floor is completed.
House L1
Finishing works on the entrances are nearing completion.
The installation of ceramic tiles has been completed.
Installation of metal-plastic windows in the commercial area is nearing completion.
Finishing of the commercial facade is in progress.
The installation of the lobby's self-leveling (decorative) floor is completed.
Installation of the staircase railing has begun.
Building L2
The facade is being completed.
Works on the installation of gypsum plaster in the apartments are completed.
House L3
The laying of the parapet is completed.
House L4
Installation of vertical elements of the 3rd residential floor has begun.
House L5
Installation of the floor slab of the 2nd residential floor is completed.