Construction state of the Manhattan UP residential area as of 01/30/2023
Section A1
The masonry of the internal walls of the 11th floor is completed.
Completed laying of the parapet.
Glazing on the 1st-4th floors has begun.
Section A2
Reinforcement of the floor slab on the 10th floor is in progress.
Laying of the internal walls of the 7th floor is completed.
Laying of the internal walls of the 8th floor is in progress.
Section A3
Installation of vertical elements of the 5th floor has begun.
Section A4
Installation of vertical elements of the basement is completed.