Construction state of Comfort Park as of 10.25.2022
Section 13
The entrances are 95% complete.
Installation of tiles in the entrances has been completed.
Section 14
Facade finishing is 90% complete.
Finishing of entrances is 80% complete.
Paving stones are 50% complete.
Tiling on the balconies is in progress.
Section 16
Works on the improvement of the courtyard are 80% complete.
Installation of screeds in the corridors is completed.
Installation of entrance doors to the apartments is 60% complete.
The installation of tiles on the balconies has begun.
Plastering of apartments on the 4th floor is in progress.
Section 17
Works on the improvement of the courtyard are 80% complete.
Works on internal gas supply have been completed.
Section 18
Installation of windows is completed.
Works on the improvement of the courtyard are 80% complete.
The facade is 40% complete.
Section 19
Completed laying of the outer walls of the 2nd floor.
Completed work on the masonry of the 1st floor.
Completed work on the masonry of the outer walls of the 2nd floor.
Works on landscaping in the outer yard are ongoing.
Section 20
Installation of the columns of the 0th floor is completed.