Construction state of Main House as of 10.21.2022
Section 1
Facade works are 50% complete.
The plastering of the apartments on the 13th floor has been completed.
Installation of internal electrical networks is in progress.
Installation of internal networks (water supply and sewage) has begun.
Section 2
Facade works are in progress.
The roof screed is completed.
Parking lot
The waterproofing of the parking lot pavement is 20% complete.
The development of the parking lot pit has begun.