Construction state of the residential complex “Avtorskyi” as of 25.10.2022
Section 1-2
Reinforcement and concreting of the vertical elements of the parking lot has been completed.
Tile installation on the penthouse terraces is completed.
Clinker tiling of penthouse walls is 90% complete.
Clinker tiling of stairwells and corridors in 1 section is 85% complete.
Reinforcement of the parking lot floor slab is in progress.
Work is underway to install internal gas supply networks.
Clinker tiling of stairwells and corridors in section 2 has begun.
Section 3-4
Installation of semi-dry screeds on the penthouse terraces and stairwell corridors has been completed.
Works on the installation of external water supply and sewage networks have been completed.
Clinker tiles on the penthouse facades are 90% complete.
Works on installation of internal gas supply networks are in progress.
Installation of aluminum structures in commercial premises is in progress.
Preparatory work has begun on the installation of entrance doors to the apartments.