Construction state of the Family Plaza residential complex 6.07.2022
Construction status of the Family Plaza residential complex as of 6.07.2022
Section 1
- Work on external sewerage networks has been completed.
- Works on internal house networks (water supply and sewerage) have been completed.
- The masonry of the external and internal walls of the commercial premises is completed.
- The entrance is being finished.
Section 2
- Facade finishing works have been completed.
- Plastering of the staircase has been completed.
- Work is underway on internal power supply networks.
- The external and internal walls of the commercial building are 90% complete.
Section 3
- Completed masonry of the internal and external walls of the basement
- Facade decoration is 70% complete.
Section 4
- Completed laying of internal and external walls of the basement
- Facade decoration is 50% complete.
Section 5
- Laying of external and internal walls of the 10th floor is in progress.
Section 6
- Concreting of vertical elements of the 6th floor is in progress.
Section 7
- Concreting of the vertical elements of the basement is underway.
Section 12
- Concreting of vertical elements of the 9th floor is underway.
- Laying of external and internal walls of the 4th floor is in progress.