Status of construction of the residential complex “IQ House” as of 26.07.2023
Section 1
Laying of the outer walls of the 3rd floor has begun.
Installation of vertical elements of the 4th floor has begun.
Installation of windows on the 2nd floor has been completed.
Completed laying of pipes for domestic sewage, rainwater, water supply and cable products.
Reinforcement of the basement slab has begun.
Section 2
Completed laying of the internal walls of the 6th floor.
Laying of the external walls of the 7th floor has begun.
Installation of the floor slab of the 8th floor is completed.
Completed laying of pipes for domestic sewage, stormwater, water supply and cable products.
Reinforcement of the basement slab has begun.
Section 3
Laying of the outer walls of the 5th floor is completed.
Installation of the floor slab of the 7th floor has been completed.
Installation of windows on the 4th floor is completed.
Completed laying of pipes for domestic sewage, rainwater, water supply and cable products.
Reinforcement of the basement slab has begun.