Status of construction of the residential complex “U ONE” as of 01.08.2023
Section 3
All monolithic works are completed.
The masonry of the outer walls of the 11th floor has been completed.
Glazing of the 9th floor is completed.
Completed laying of the internal walls of the 6th floor.
Plastering of staircases is in progress.
Section 4
Installation of the floor slab of the 11th floor is in progress.
Laying of external walls of the 5th floor is in progress.
Section 2
Installation of the floor slab of the 7th floor is in progress.
Section 1
Installation of monolithic grillage is 95% complete.
Installation of vertical elements of the 1st floor is 80% complete.
Works on the installation of external water supply and sewerage networks are in progress.