The state of construction of a residential array “Parkova Alley” on 18.10.2019.
Section 15
Work continues on the plaster walls of apartments.
Continues the insulation and decoration of Cokolnoï part of the façade from the inner part of the yard.
Section 14
Work continues on the plaster walls of apartments.
Sections 14 and 15 are accomplished finishing the entrance.
Started work on the installation of paving slabs from the inner part of the Courtyard section 15.
The finishing of entrances to section 12-13 was started.
Section 11
Installation of window systems in commercial premises has been completed
Section 6-7
Completed development of the pit.
Section 8
The construction of the 5th floor was started.
Section 9-10
The 4th floor was completed.
Section 2-2 A
Completes the device of columns and walls of the staircase basement floors.