Новини
04.09.2023
Construction status of the residential complex “Main House” as of 04.09.2023
Section 1 Finishing of entrances is completed. Glazing of the commercial floor is completed. Installation of elevators has been completed....
01.09.2023
Сonstruction state of the residential complex “U ONE” as of 01.09.2023
Section 3 The masonry of the outer walls of the 13th floor has been completed. Glazing of the 10th floor...
29.08.2023
Construction stateof the Parkova Alley residential complex as of 29.08.2023
Section 3 Interior finishing works are 90% complete. Installation of the elevator is completed. Section 3a The interior decoration is...
29.08.2023
Construction state of the Union residential complex as of 29.08.2023
Section 3 The interior decoration is 90% complete. Installation of the elevator is completed. Section 3a The interior decoration is...
28.08.2023
Construction state of the residential complex “IQ House” as of 28.08.2023
Section 1 The masonry of the internal walls of the 4th floor is completed. Installation of windows on the 3rd...
24.08.2023
Franko River Club cottage community | 24.08.2023
Franko River Club is a cottage community where each house has its own personal style, without disturbing the holistic perception...