31.10.2023
Construction state of the SKYGARDEN residential complex as of 31.10.2023
Section 1 Installation of vertical elements of the 1st floor is completed. Formwork of the 1st floor slab is completed....
26.10.2023
Construction state of the Union residential complex as of 26.10.2023
Section B The hall is 90% finished. Section C The hall is 90% finished. Section D Completion of the external...
25.10.2023
Construction state of the Parkova Alley residential complex as of 25.10.2023
Section 3 Interior finishing works have been completed. Installation of doors has been completed. Gas supply to the apartments has...
24.10.2023
Construction state of the IQ House residential complex as of 24.10.2023
Section 1 Reinforcement of the floor slab on the 8th floor has been completed. Waterproofing of the foundation is 70%...
18.10.2023
Franko River Club cottage community | 18.10.2023
Franko River Club is a cottage community where each house has its own personal style, without disturbing the holistic perception...
17.10.2023
Construction dynamics of Family Plaza: April – October 2023
More construction means more changes in the territory of the residential complex. Every month, Family Plaza becomes more beautiful and...