05.10.2023
Construction state of the residential complex “A5” as of 05.10.2023
✅Sections 1-2 Laying of the internal walls of the 8th and 11th floors is completed. The masonry of the internal...
04.10.2023
Construction state of the IQ House residential complex as of 04.10.2023
Section 1 The masonry of the basement walls is completed. Concreting of the walls and columns of the 8th floor...
03.10.2023
Dynamics of construction of the Parkova Alley residential area: February – September 2023 💚
We continue to build our projects without resting on our laurels. Every month we are getting closer to the completion...
03.10.2023
Construction state of the residential complex “MAIN HOUSE” as of 03.10.2023
Section 1 Facade works on the commercial floor are 50% complete. Section 2 Installation of the hinged-ventilated facade is 25%...
02.10.2023
Dynamics of construction of the residential complex “Union”: April – September 2023
Every month we assess the growth of new sections and record changes at the construction site. Find out about the...
02.10.2023
Construction state of the U ONE residential complex as of 02.10.2023
Section 3 The glazing of the 11th floor has been completed. Glazing of the 12th floor is 95% complete. Laying...