Новини
23.03.2023
Construction state of the Manhattan residential area as of 23.03.2023
House 5 The entrance is 100% finished. Installation of balcony railings is in progress. House 6 Installation of metal-plastic glazing...
21.03.2023
Construction dynamics of RC A5: January – March 2023
We report on the growth of the modern business-class residential complex in the heart of Ivano-Frankivsk, the A5 residential complex....
21.03.2023
Construction state of the Comfort Park residential area as of 21.032023
Section 13 Installation of stair railings has been completed. Reinforcement of the gas pipe along the facade is underway. Section...
20.03.2023
Construction state of the Family Plaza residential complex as of 20.03.2023
Section 1 Transferred to the management company. Section 2 Finishing of the hall is completed. Section 3 Finishing of the...
17.03.2023
Construction state of the residential complex “Avtorskyi” as of 17.03.2023
Section 1-2 The installation of glass fencing on the penthouse terraces has been completed. The walls of commercial floors are...
16.03.2023
Construction state of the IQ House residential complex as of 03.16.2023
Section 1 The construction of vertical elements of the 2nd floor has begun. Concreting of the floor slab of the...