16.02.2023
Construction state of the U ONE residential complex as of 02.16.2023
Section 3 Installation of vertical elements of the 4th floor is completed. Section 4 Completed work on the pressing of...
16.02.2023
Construction state of the residential complex “A5” as of 02.16.2023
The exterior walls of the 5th floor are 60% complete. Laying of the internal walls of the 4th floor is...
15.02.2023
Construction state of the residential complex “IQ House” as of February 15, 2023
Section 1 Installation and concreting of the 1st floor has been completed. The construction of vertical elements of the 2nd...
10.02.2023
Construction state of the residential complex “MAIN HOUSE” as of 10.02.2023
Section No. 1 Facade works are 80% complete. Entrances are 30% finished. Installation of entrance doors to apartments has begun....
10.02.2023
Special offer! Up to -6% discount on your own kissing spot
We love you and give you pleasant discounts of up to -6% for all apartments and -8% for parking spaces...
08.02.2023
Updated photos of the Royal Hall residential complex on 08.02.2023
Royal Hall is a residential complex that emphasizes your status! 💎 Walking access to all the most important locations of...