Новини
09.05.2023
Construction state of the residential complex “Avtorskyi” as of 09.05.2023
Sections 1-2 Finishing works on the stairwells in section 2 have been completed. Installation of elevators in sections 1-2 has...
05.05.2023
Construction state of the residential complex A5 as of 05.05.2023
Sections 1-2 Completion of the exterior walls of the 7th floor. The masonry of the internal walls of the 6th...
04.05.2023
Construction state of the residential complex “IQ House” as of 04.05.2023
Section 1 Laying of the external and internal walls of the 1st floor has begun. Section 2 Laying of the...
03.05.2023
Construction state of the residential complex “MAIN HOUSE” as of 03.05.2023
Section 1 The entrances are 90% finished. Installation of heating networks is 80% complete. Section 2 Installation of aluminum facade...
02.05.2023
Construction state of the residential complex “U ONE” as of 02.05.2023
Section 3 Installation of vertical elements of the 8th floor is completed. Installation of the floor slab of the 8th...
01.05.2023
Section 2 of the Family Plaza residential complex is put into operation
Another good news for the owners of apartments in this special residential complex. Despite the difficult conditions, the blago team...